Innisfail · Case study

Innisfail gym: old unit out, 12.5kW Mitsubishi in.

Mitsubishi Heavy Industries 12.5kWPappy's GymInnisfail
CoolAug 2026
Innisfail
01 12.5kW New Mitsubishi system
02 2 Visits
03 21 Photos from the job
04 Innisfail Where

Stop by stop

5 stops on the job

  1. Existing ceiling-mounted air conditioner above windows inside an Innisfail gym
    Cool01/05
    Gym floor

    Gym floor

    The old under-ceiling head sat high on the wall above the gym windows.

  2. Old mould-covered outdoor air conditioner with drill and tools in Innisfail
    Cool02/05
    Old condenser

    Old condenser

    The outdoor unit was heavily soiled with mould and moss.

  3. Old outdoor air conditioner compressor exposed during removal in Innisfail
    Cool03/05
    Panels off

    Panels off

    Cover off, the compressor showed the state of the internals. It had done its time.

  4. New Mitsubishi Heavy Industries condenser on a pallet beside a service ute in Innisfail
    Cool04/05
    New arrival

    New arrival

    The new Hyper Inverter condenser turned up on a timber pallet.

  5. Refrigeration pipework and cabling run up a corrugated wall in Innisfail
    Cool05/05
    Up the wall

    Up the wall

    Refrigeration pipework and cabling run up the corrugated wall.

Drag to compare

Same corner, new unit

New Mitsubishi Heavy Industries Hyper Inverter outdoor unit installed at an Innisfail gym
Technician dismantling an old twin-fan outdoor condenser at an Innisfail gym
Before After
The old twin-fan condenser coming apart, and the new Hyper Inverter in the same corner.
Technician on a ladder running pipework to a new outdoor unit at an Innisfail gym

The tricky bit

Working off the ladder

We ran the refrigeration pipework and cabling up the corrugated wall, working off a ladder to reach the internal head.

The result

New system, same corner

The old under-ceiling unit and its weathered condenser are gone, and Pappy's Gym now runs on a new Mitsubishi Heavy Industries 12.5kW system. The outdoor unit sits in the same corner with the pipework run up the wall, ready for the Innisfail heat.

Running 6 Aug 2026

Brand
Mitsubishi Heavy Industries
System
12.5kW Hyper Inverter
Removed
Old under-ceiling system
Where
Innisfail
Full job notes

From an aged, mould-covered outdoor unit to a new Mitsubishi Heavy Industries 12.5kW install.

Pappy's Gym in Innisfail had an old under-ceiling air conditioner that had reached the end of its run. The outdoor condenser was heavily soiled with mould and moss, and the internal head unit sat high on the wall above the gym windows. We were called in to remove the old system and install a new Mitsubishi Heavy Industries 12.5kW unit.

We started at the outdoor unit. The old twin-fan condenser came apart panel by panel. Once the cover was off you could see the compressor and the state of the internals. It had done its time. We dismantled it and got it off the wall.

Inside, the old under-ceiling head unit was pulled down from above the windows. That side of the gym looks out over town, so we kept the run tidy against the corrugated wall.

The new Mitsubishi Heavy Industries Hyper Inverter condenser turned up on a timber pallet and we positioned it against the exterior wall in the same corner. From there we ran the refrigeration pipework and cabling up the wall, working off a ladder to reach the internal head. Drainage went in beside the pipe run.

With the new outdoor unit set in place, we finished off the connections up top. This was a like-for-like replacement done in two visits, with the removal on the first and the new unit going in on the second.

Commercial spaces like a gym cop a fair bit of heat from bodies and equipment, so a unit sized right for the room matters. The 12.5kW suits the space above the windows where the old head used to hang.

We do this sort of work across the region. If you want to see more, have a look at our other jobs around Innisfail. It's straightforward work, but a fresh unit makes a difference for a room full of people.

Mitsubishi Heavy Industries 12.5kW

A new Hyper Inverter unit sized for the gym floor, replacing the old under-ceiling system above the windows.

Full removal and replacement

The aged outdoor condenser and internal head unit were both taken out before the new gear went in.

Tidy pipe run

Refrigeration pipework, cabling and drainage were run up the corrugated exterior wall and kept neat.

3D Airconditioning ute parked beside the new outdoor condenser unit at a commercial building in Innisfail New Mitsubishi Heavy Industries outdoor unit installed beside a 3D Airconditioning ute in Innisfail Technician on a ladder running pipework to a new outdoor unit at an Innisfail gym Refrigeration pipework and cabling run up a corrugated wall in Innisfail New Mitsubishi Heavy Industries condenser on a pallet beside a service ute in Innisfail New Mitsubishi Heavy Industries Hyper Inverter outdoor unit installed at an Innisfail gym Old under-ceiling air conditioner mounted high on a wall inside an Innisfail gym Existing ceiling-mounted air conditioner above windows inside an Innisfail gym Old under-ceiling air conditioner viewed against gym windows in Innisfail Gym interior in Innisfail with old ceiling air conditioner and exercise equipment Old weathered outdoor air conditioning unit beside a 3D Airconditioning ute in Innisfail Aged outdoor condenser unit and gas bottles beside a service ute in Innisfail Technician working on an old outdoor air conditioner beside a service ute in Innisfail Technician removing an old mould-covered outdoor air conditioner in Innisfail Technician working on old outdoor unit against a corrugated wall in Innisfail 3D Airconditioning ute loaded with ladders parked at an Innisfail commercial building Technician working beside removed old air conditioner panel at an Innisfail building Old mould-covered outdoor air conditioner with drill and tools in Innisfail Interior of an old outdoor condenser unit exposed during removal in Innisfail Old outdoor air conditioner compressor exposed during removal in Innisfail Technician dismantling an old twin-fan outdoor condenser at an Innisfail gym

What we did

  • Removed the old twin-fan outdoor condenser, heavily soiled with mould and moss
  • Pulled down the old under-ceiling head unit mounted above the gym windows
  • Positioned the new Mitsubishi Heavy Industries 12.5kW Hyper Inverter outdoor unit against the exterior wall
  • Ran refrigeration pipework and cabling up the corrugated wall
  • Installed drainage alongside the pipe run
  • Completed the connections and set the new system running